Sep. 04, 2003 Online Since 1996 Vol 78 No. 3

The Appalachian | News | Business Affairs

Bankruptcy, architectural problems further delays By David Forbes
Senior Staff Writer
   Construction at several areas in the center of campus is behind schedule, making travel more difficult.
    Building projects, including the solarium on Plemmons Student Union and the University Bookstore construction, are running behind due to a variety of problems, including the bankruptcy of one of the mechanical contractors, said Clyde D. Robbins, director of design and construction.
    “We’re behind schedule on the student union and the bookstore, and we have very little leverage, these are low-bid contractors,” Robbins said.
    Robbins said one of the problems was that a mechanical contractor working on the solarium project had gone bankrupt, delaying construction of several other parts of the project.
    This is not the first time Appalachian State University has faced this problem.
    Last year a contractor working on the Living-Learning Center went bankrupt, causing delays.
    Robbins said that a third party scheduler has been hired to figure out ways to speed up construction, and that the solarium and student union construction would hopefully be finished by January 2004 instead of the current expected time of March.
    The solarium was originally scheduled to be finished last November.
    Currently, there are only three open entrances to the student union, a problem that has been delaying traffic around campus.
    “I think [the construction problems] are a huge inconvenience to students and others that use this building. A common route for students is to go to the post office and then to the union. You can still do that, but it’s not as easy,” said David L. Robertson, director of Student Programs. “This is one of the worst examples of construction delays I’ve ever seen on campus.”
    Construction on the post office is due to be completed in two weeks, while the University Bookstore construction is scheduled to be finished late 2004-05, according to information from the Office of Business Affairs
    A temporary sidewalk was supposed to be constructed by the beginning of fall semester so students could access the back entrance to the student union near Greenbriar Theatre, Robertson said.
    Architecture problems delayed that project, which is supposed to be complete within the next two weeks.
    Student workers in the student union said they viewed the construction as a minor inconvenience.
    “I haven’t really had any problems, though it’s a little difficult to get around sometimes. But this is my first year here, so I was kind of expecting this,” said Laurin Robertson, a freshman forensic science major who works in the Center for Student Involvement and Leadership.
    Patty Troxler, a freshman recreational management major who works at the information desk, agreed.
    “No, it’s not really a problem, but that’s only because I haven’t been here that long. I can’t really compare it to earlier,” Troxler said.
    Construction around the post office affects postal employees.
    “It makes things a little inconvenient, but they’d be working in here anyway, but a lot of the construction hasn’t really started yet,” said Mark Lunsford, a window clerk at the post office.
Email Us