Home arrow News arrow Campus arrow Anticipation mounts as SRC opening nears
   
   
Sunday, 22 November 2009
 
Your Voice
What form of travel do you plan on taking for the holiday break?
 





Lost Password?
No account yet? Register

Anticipation mounts as SRC opening nears
Thursday, 13 April 2006
by MALLORI MORRIS
News Reporter


Get ready to lace up those tennis shoes and grab a water bottle. Months of anticipation for the Student Recreation Center’s opening will end when its doors open at 4 p.m. Tuesday.

Contractors were given the OK to open the 120,000 square feet facility April 6, with only a minor “punch list” of items still left to be completed over the next 30 days, said Dr. Clyde D. Robbins, director of Design and Construction.

Paint touch-ups, carpet cleaning and mechanical tune-ups are among tasks left to complete.

“I think it’s a great building,” Robbins said. “It’s well built and students are really going to like and be able to use what’s on the inside.”

The facility houses a 50-feet climbing wall, cardio theatre, a weight room area, an indoor running/walking track, a 50-meter swimming pool and University Recreation offices.

Another four to six weeks are needed to complete the juice bar, Robbins said.

Because Appalachian did not receive the Certificate of Occupancy until late last week, cardio equipment and weights are still on order and SRC directors are unsure whether the equipment will arrive in time.

“We can’t order stuff until we have somewhere to deliver it to,” said Karen D. Walter, a SRC coordinator.

Walter said the new SRC does have some weight lifting equipment in the building but is not fully stocked yet. Cardio equipment and machines are still en-route to the facility as of this week.

Students hired to work at the new SRC have been training this week. Over 200 new student employees will work at the SRC, University Recreation Director Joe R. Carter said.

Carter said recreation staff worked with student employees during the construction process outside the facility to make it easier on opening day.

“With a building this size there are a lot of things that need to be done … it’s actually opening early,” he said.
Carter explained contractors had a Feb. 28 guaranteed completion date with a 30-day extension for additional construction. This would put opening at April 30, but the facility will now open 12 days early.

“Students [need to] be patient, just because there are signs up that say we’re open Tuesday, that doesn’t mean we’re open yet,” Carter said.

Trackback(0)
Comments (0)Add Comment

Write comment
You must be logged in to post a comment. Please register if you do not have an account yet.

busy
 
 

Advertisement

 

© Copyright 1996 - 2008 The Appalachian | theapp.appstate.edu
Advertise with the ASU Student Media